New Animal Shelter

Live Feed:


May 2020

Image-16

April 22, 2020

Our structural steel arrives and the building begins to take vertical form.

Image-15

April 16, 2020

The foundation is poured--the very basis of everything that this shelter will provide to the animals and community is laid.  The view here is from Shady Brook Dr. facing north.  The left side of the foundation is where the shelter vehicles enter.  The middle of the building is the public entrance.  To the right, there is a community room and outdoor courtyard for dogs and people.

A concrete machine pours concrete slab.

January-March 2020

The site is prepared.  Much of the work that happens is underground with utilities.  Earthwork happens to level the site.  The site sloped down in elevation to the north so fill dirt needed to be brought to the site.

IMG_2911


IMG_2866



Empty lot of dirt being prepped for construction

Layout of foundation on dirt lot

December 17, 2019

The shelter, built in 1992, is demolished.

IMG_2699

IMG_2700

Gray building being demolished by equipment

Pile of building rubble being cleared

November 19, 2019

The doors of the old 500 Shady Brook Dr. close for the final time.

Gray animal shelter building--built in 1992